Divercity Waterloo in the News - 9 of August 2011

9 August 2011
Stage 1 Level 4 was poured with the Precast for the entire floor also being erected last week.

Stage 2 Level 2 Precast panels were erected last week along with Stage 3 Ground Floor.

Stage 5 Level 4 has 20% of the Precast erected with the slab being expected to be poured later this week.

  Hebel has been installed to all Stage 1 Ground Floor and Level 1 apartments with Level 2 set-out commencing this week.

The services trades (hydraulic, mechanical & electrical) are currently running their services through the apartments and risers.  

Click hereto read the article.