Divercity Place Construction Update - 9 of September 2011
Current Stage of Construction – 9 September 2011
A milestone was reached on 2/9/11 when the last pour for the Podium deck was completed! The last pour totalled 490m3 of concrete!
Stage 1 Level 6 is anticipated to be poured at the
end of this week.
Internal finishes continue with the commencement of
Plasterboard and installation of stairs to Stage 1 Ground Floor
units. The stairs for Level 1 have already been ordered and due to
be delivered late next week for installation.
Hebel works have now progressed to Stage 5 Level 2
working their way down to Level 1 then Ground
Floor.
The Services trades are following the metal stud
framing and are now currently completing rough-in for Stage 1 Level
1 & commencing on Level 2 apartments.
.