Divercity Place Construction Update - 29 of August 2011

Current Stage of Construction – 29 August 2011

Hebel to Stage 1 Level 3 and Stage 5 Level 2 has commenced whilst Stage 1 Ground Floor and Level 1 has all metal studs erected, ready for Plasterboard once the services rough-in is complete.

The Services trades have now completed rough-in to Stage 1 Ground Floor and are currently completing Stage 1 Level 1 and beginning on Stage 1 Level 2.

The stairs for apartments in Stage 1 Ground Floor and Level 1 are currently being manufactured and are expected to be installed at the end of this week.

Stage 2 Level 2 Precast panels were erected last week along with Stage 3 Ground Floor.

Stage 5 Level 4 has 20% of the Precast erected with the slab being expected to be poured later this week.

  Hebel has been installed to all Stage 1 Ground Floor and Level 1 apartments with Level 2 set-out commencing this week.

The services trades (hydraulic, mechanical & electrical) are currently running their services through the apartments and risers.