Construction Update 27 July 2011

Divercity Place Construction Update - 27 July 11

Current Stage of Construction – 25 June 2011
Due to the severe rains last week, progress at Divercity was limited. But nonetheless we were able to pour Stage 5 Level 3.
The crane was also raised an extra 2 towers on Monday (12 meters).

Looking ahead, Precast panels will be erected on Stage 5 Level 3 & Stage 2 Level 1 with formwork to follow straight afterwards.

The internal finishes for Stage 1 apartments have also commenced today with the Hebel & Plastering subcontractor starting on-site.

 