Divercity Place Construction Update - 20 of December 2011
Current Stage of Construction – 20 December 2011
The roof on Stage 1 has now been completed with the roofers now moving onto Stage 5. The final slab has been poured on Stage 2 which was followed with the erection of precast panels . This now concludes all concrete slabs for Stage 1, 2 & 5.
The scaffold along Stage 1 North has been dismantled exposing
the newly painted & rendered façade. This is a glimpse of what
the building in its entirety will look like.
Window installation to Stage 1 is now primarily complete with
only Level 6 remaining, with Stage 2 and Stage 5 up to Level 4
installs. The entry to the carpark will now be secured with
the recent installation of the roller door.
Services have now begun fit-off on Stage 1 Ground Floor
apartments with bath & laundry tubs being installed. The LED
downlights & pendant lights are also being installed in Ground
Floor and Level 1 apartments . Plasterboard has been
completed on Stage 1 Level 5 with Hebel & Stud works currently
80% complete on Level 6. Stage 5 now has Ground Floor, Level 1,
Level 2 and Level 3 sheeted with Level 4 to follow first thing next
year along with ceiling grids to all floors.
Tiling works continue through Stage 1 with apartments from
Ground Floor through to Level 3 now complete. Joinery works are
following through and havenow installed all Kitchens & Bathroom
vanities to Stage 1 Ground Floor apartments. Public Domain
works are on-going with the kerbs now completed for Sydney
Gate.