Divercity Place Construction Update - 18th July 2011

Divercity Place Construction Update - 18 July 11

18 July 2011
Stage 1 Level 3 Precast panels have been erected with formwork due to complete early this week.

Stage 2 Level 1 has now been poured with Precast panels due to be erected early this week.

Stage 5 Level 3 formwork is now complete. The deck is ready for concrete to be poured early this week. Blockwork to the Basement & Ground Floor has commenced.

Basement works are now 60% complete. Formwork to the Basement has now been completely stripped and removed.

The crane is also being raised an extra 4 towers (24 meters) today.

 