Divercity Place Construction Update - 16 of February 2012
Current Stage of Construction – 16 of February 2012
This week there is a lot happening with stage 1 well under way and stage 2 & 5 tracking well. The rain in Sydney has caused a few delays in some areas but that is not stopping the team from getting the job done.
I am thrilled to show you some pictures this week of the new park going in at Divercity Block B Stage 1, really exciting.
With the completion of Stage 2 Precast, the
structural steel for the roof can now be completed. Stage 1 façade
is almost complete with the Alucobond works to the Eastern
Elevation is now complete.
Window installation to Stage 2 is now complete with
Stage 5 Level 5 windows currently outstanding.
Plasterboard works to Stage 1 is now complete with
Level 5 corridor ceilings being sheeted this week. Stage 5 wall
sheeting is now complete and are now sheeting the ceilings. Stage 2
services rough-ins are currently completing Level 4 with Level 3
already sheeted.
Tiling works have commenced onto Level 5 (Stage 1)
with only a few apartments remaining. Carpet has also been laid up
to Level 3 apartments. Joinery works have also commenced on Level 5
and will be complete in the coming week.
Balcony balustrades for Stage 1 apartments will also
be completed by the end of this week.
North Park has progressed significantly this week with
the commencement of landscape works.
Check out the new Cafe in the area Young St, Bocata Deli &
Cafe and I believe there is a very interesting new auction
house opened up where you might be able to find a wonderful
treasure, http://www.vickhoad.com/v2/index.asp