Divercity Place Construction Update - 13 of September 2011
Current Stage of Construction – 13 September 2011
Stage 2 Level 3 was poured late last week followed by the erection of precast panels.
North Park civil works have begun along with Sydney
Gate works.
Plasterboard sheeting to Stage 1 Level 1 has
commenced with Hebel and stud work currently being installed on
Stage 1 Level 3 and Stage 5 Level 1. The ceiling grid to Stage 1
Ground Floor apartments has also commenced today.
Services are still following the metal stud framing
and are currently completing Stage 1 Level 2 rough in and due to
commence Stage 1 Level 3 stack work & rough-in's later this
week.
.