Divercity Place Construction Update - 11 July 11
Stage 1 Level 3 is now completely poured. Precast panels are being erected this week with the formwork to follow.
Stage 2 Level 1 steel reinforcement is finishing up
with concrete to follow within the next few days.
Stage 5 Level 3 Precast panels have been erected with
formwork commencing.
Blockwork to the Basement & Ground Floor has
commenced. Basement works are now 50% complete.
Services to the basement are continuing progressively
as the formwork is being removed.
Stage 1 Ground Floor apartments will be prepared for
finishes trades this week.