Divercity Place Construction Update - 16 of February 2012


Current Stage of Construction – 16 of February 2012
This week there is a lot happening with stage 1 well under way and stage 2 & 5 tracking well. The rain in Sydney has caused a few delays in some areas but that is not stopping the team from getting the job done.
I am thrilled to show you some pictures this week of the new park going in at Divercity Block B Stage 1, really exciting.

Read more ...


Divercity Place Construction Update - 23 of January 2012


Current Stage of Construction – 23 of January 2012
The roof structure on Stage 5 is now complete with Stage 2 roof currently underway.

Read more ...


Living the high life - SMH 7 January 2012


Living the high life - SMH
Domain - 7 of January 2012

Read more ...


Divercity Place Construction Update - 20 of December 2011


Current Stage of Construction – 20 December 2011
The roof on Stage 1 has now been completed with the roofers now moving onto Stage 5. The final slab has been poured on Stage 2 which was followed with the erection of precast panels . This now concludes all concrete slabs for Stage 1, 2 & 5.

Read more ...


Divercity Place Construction Update - 23 of November 2011


Current Stage of Construction –23 of November 2011
Stage 1 Roof Sheeting is now at 80% completion with Stage 2 Level 4 Precast panels being placed on the recently poured slab.

Read more ...


Divercity Place Construction Update - 4 of November 2011


Current Stage of Construction –4 November 2011
Structural Steel Roofing Works are complete to Stage 1, with Roof Sheeting now started. Stage 2 Structure continues, with Level 4 concrete now poured.

Read more ...


Divercity Place Construction Update - 7th of October 2011


Current Stage of Construction – 7/10/11
Structural Steel Roofing Works have commenced to Stage 1. Stage 2 Structure continues, with Level 4 formed, steel in place and is ready for concrete.

Read more ...


Divercity Place Construction Update - 13 of September 2011


Current Stage of Construction – 13 September 2011
Stage 2 Level 3 was poured late last week followed by the erection of precast panels.

Read more ...


Divercity Place Construction Update - 9 of September 2011


Current Stage of Construction – 9 September 2011
A milestone was reached on 2/9/11 when the last pour for the Podium deck was completed! The last pour totalled 490m3 of concrete!

Read more ...


Divercity Place Construction Update - 29 of August 2011


Current Stage of Construction – 29 August 2011

Read more ...


Divercity Waterloo in the News - 9 of August 2011


9 August 2011
Stage 1 Level 4 was poured with the Precast for the entire floor also being erected last week.

Read more ...


Why one-bedders are winners - SMH 30 of July 2011


Why one-bedders are winners – SMH 30 July 2011
Domain - 30 of July 2011

Read more ...


Divercity Place Construction Update - 27 July 11


Current Stage of Construction – 25 June 2011
Due to the severe rains last week, progress at Divercity was limited. But nonetheless we were able to pour Stage 5 Level 3.
The crane was also raised an extra 2 towers on Monday (12 meters).

Read more ...


Divercity Place Construction Update - 18 July 11


18 July 2011
Stage 1 Level 3 Precast panels have been erected with formwork due to complete early this week.

Read more ...


Divercity Place Construction Update - 11 July 11


Stage 1 Level 3 is now completely poured. Precast panels are being erected this week with the formwork to follow.